As discussed with you, I have already completed the identification of tasks at the granular level for all the modules except for Finance & Costing. The granular activities has been identified by all their respective module leaders.
I have reminded the Finance & Costing team to complete the identification of their granular activities by tomorrow 11.00 am. I will review the details with them tomorrow afternoon
Based on the current progress so far, I will be able to submit you the ‘PROJECT PLAN – draft ver 7.0 , which will include all the granular details, by tomorrow night (11/04/2013).
I will need your cooperation in completing the above details in your modules by 11.00 am tomorrow morning.
I am attaching the above document for your INPUTS. Please read carefully the following :
For each of the ‘PENDING UAT SCENARIOS’, mentioned in column-A , in the attached file , we have further sub-divided them into the following activities
Sorry for the delay in sending the project plan due to some workload.
I have completed the task please find the attached file for GL, AR, CM module details.
Thanks, Finance Consultant. If you have time, I will request you to spend some time with Costing Consultant in guiding her for the AP modules as well.
Can you send me for the Costing & AP modules by tomorrow 11.00 am ? Can you guide Pooja for the AP modules. Can you guide Pooja for the Costing modules.
I have reminded the Finance & Costing team to complete the identification of their granular activities by tomorrow 11.00 am. I will review the details with them tomorrow afternoon
Based on the current progress so far, I will be able to submit you the ‘PROJECT PLAN – draft ver 7.0 , which will include all the granular details, by tomorrow night (11/04/2013).
I will need your cooperation in completing the above details in your modules by 11.00 am tomorrow morning.
I am attaching the above document for your INPUTS. Please read carefully the following :
For each of the ‘PENDING UAT SCENARIOS’, mentioned in column-A , in the attached file , we have further sub-divided them into the following activities
Sorry for the delay in sending the project plan due to some workload.
I have completed the task please find the attached file for GL, AR, CM module details.
Thanks, Finance Consultant. If you have time, I will request you to spend some time with Costing Consultant in guiding her for the AP modules as well.
Can you send me for the Costing & AP modules by tomorrow 11.00 am ? Can you guide Pooja for the AP modules. Can you guide Pooja for the Costing modules.